CSR & Airflow

Alterations and Changeouts
Climate Zone Duct Test and Seal Refrigerment Measurement Airflow Measurement Fan Watt Draw
1 Not Required
2 Required Not Required
3-7 Not Required
8 Not Required Required Not Required
9 Required Not Required
10-15 Required Not Required
16 Required Not Required
Alterations and Changeouts
with New Ducts and Equipment
Climate Zone Duct Test and Seal Refrigerment Measurement Airflow Measurement Fan Watt Draw
1 Not Required
2 Required Not Required
3-7 Not Required
8 Not Required Required Not Required
9 Required Not Required
10-15 Required
16 Required Not Required

The 2008 Standards

The New Standards, due August 1, 2009, have been delayed until January 1, 2010. Under the new Residential Title 24 Compliance Standards, TXV verifications will no longer be accepted, but will be replaced by the identification of refrigerants(R-22 or R-410a) and metering devices(capillary, piston, orifice, or TXV) for RCM(Refrigerant Charge Measurement) on split systems only. Additional measures: Airflow Measurement and Fan Watt Draw, will also be required when existing duct is completely replaced. Pressure Testing and Duct Sealing will also be required for both package air conditioning and split air conditioning systems on new or existing installations under the 2008 Standards.

Temperature: 57.0
Dew Point: 46.9
Relative Humidity: 68%
Monday Feb 8th, 2010
Phone: 916-730-2233
Fax: 916-924-1195
rjwin@acpressuretest.com
csrairflow@acpressuretest.com
Climate Zone 16: Burney Mountain and Big Bend, Shasta, Big Creek, Fresno...